Answer :
Answer:
B) $38,400
Explanation:
The total manufacturing cost for Job No. 953 is given by sum of the direct materials, direct labor and machine costs. Direct materials cost was already stated; Direct labor and machine costs are calculated by multiplying their hours worked or used by their respective hourly rates:
[tex]C = \$16,800+(600*\$16.00)+(400*\$30.00)\\C=\$38,400[/tex]
The total manufacturing cost is $38,400