Answer :
Answer:
Please see excel attached for the calculation
1. Payback period:
Project A: 3.4 years
Project B: 2.23 years
2. If applying the payback criterion, I will choose Project B
3. discounted payback period:
Project A: 3.72 years
Project B: 2.74 year
4. If applying the discounted payback criterion, I will choose Project B
5. NPV:
Project A is $75,722
Project B is $14,078
6. If applying the NPV criterion, I will choose Project A
7. IRR:
Project A is 18%
Project B is 25%
8. If applying the IRR criterion, I will choose Project B
9. Profitability Index = present value of future cash flow/ initial investment
Project A: 1.23
Project B: 1.30
10. If applying the Profitability Index criterion, I will choose Project B
11. Choose Project B because it's have 4 in 5 criterion better than Project A
Explanation:
Year 0 1 2 3 4
Project A $(364,000) $46,000 $68,000 $68,000 $458,000
Project B $(52,000) $25,000 $22,000 $215,000 $175,000
1. Pay back period:
Project A: break even in year 4 because cash in year 1, 2, 3 = $46,00 + $68,000 + $68,000 = $182,000 < total investment $364,000
payback period = 3 years + (total investment - sum of cash in year 1, 2, 3)/ cash in year 4 = 3 + (364,000 - 182,000)/458,000 = 3.4 years
Project B: break even in year 3 because cash in year 1, 2 =$25,000+$22,000= $47,000 < total investment $52,000
payback period = 2 years + (total investment - sum of cash in year 1, 2)/ cash in year 3 = 2 + (52,000 - 47000)/215,000 = 2.23 years
2. Choose Project B because payback period is shorter
3. We have to calculate present value of cash flow to have Discounted Cashflow as below:
Project A $(364,000) $41,441 $55,190 $49,721 $301,699
Project B $(52,000) $22,523 $17,856 $15,721 $11,528
Same as above, we can calculate discounted payback period:
Project A: 3.72 years
Project B: 2.74 year
4. Choose project B because discounted back back is shorter
5. We can use excel to calculate net present value of project = NPV (rate,cash from year 0-year 4)
Project A is $75,722
Project B is $14,078
6. Choose Project A because NPV is higher
7. We can use excel to calculate internal Rate of return (IRR) of project = IRR(cash from year 0-year 4)
Project A is 18%
Project B is 25%
8. Choose Project B because IRR is higher
9. Profitability Index = present value of future cash flow/ initial investment
Project A: 1.23
Project B: 1.30
10. Choose Project B because Profitability Index is higher
11. Choose Project B because it's have 4 in 5 criterion better than Project A