Answer :
Answer:
A) Both NPV and going-in IRR to increase
Explanation:
The company's weighted average cost of capital (WACC) includes both equity and debt, and if the cost of equity is higher than the cost of debt, an increase in the percentage of debt will lower the company's WACC. The WACC is used as the discount rate to calculate the net present value (NPV) of the project.
If the discount rate is lower, then the present value of the cash flows will be higher, increasing the NPV. The internal rate of return (IRR) is the interest rate required for the NPV to be equal to $0, so if the NPV increases, then you need a higher interest rate to make it equal $0 (therefore the IRR is higher).