Answer :
Answer:
Maximum daily production rate= 6.125 units per day.
Minimum daily production rate= 75.38 units per day
Explanation:
Production rate is defined as the number of units of a product that is produced in a process in unit time.
In this instance we are to calculate the production rate per day.
It is given that a cycle consists of 40 activities. Completion time for 40 activities is 80 minutes.
Daily production rate = Total time of production/Time to complete one cycle
Maximum daily production rate= 490/80= 6.125 units per day.
Minimum daily production rate= 490/6.5= 75.38 units per day