Answer :
Answer:
b. 328,000
Explanation:
The cost of jobs completed in February.
= DM+ OH applied + DL
$96,000 + $119,000 + $113,000 = = $328,000.
Answer:
b. 328,000
Explanation:
The cost of jobs completed in February.
= DM+ OH applied + DL
$96,000 + $119,000 + $113,000 = = $328,000.