A team of engineers and architects has been formed to work on the construction of a bridge. The team will work together on-site till the construction of the bridge is complete. Thereafter, it will be dissolved. This team is an example of a(n)_____.
a) self-designing team.
b) advisory team.
c) project team.
d) virtual team.

Answer :

Answer:

c) project team.                              

Explanation:

The project team is also referred to as the programme team and consists of a group of different individuals with complementary and appropriate specialist, professional, and technical skills. Under the guidelines of a project manager or programme manager, a specific team is responsible for leading specified work that is being detailed in the project or programme plan.

The correct answer to the question is the project team.