Answer :
Answer:
The correct answer is $645,000.
Explanation:
According to the scenario, the computation of the given data are as follows:
We can calculate the Maintenance Department's cost allocated to Department A using the direct method are as follows:
Cost allocated = Maintenance Department's costs × Machine hours of Dept. A ÷ ( Machine hours of Dept. A + Machine hours of Dept. B )
By putting the value, we get
Cost Allocated = $728,850 × 3,000 ÷ ( 3,000 + 390)
= $728,850 × 3,000 ÷ 3,390
= $645,000