Answered

Production estimates for August are as follows:
Estimated inventory (units), August 1 12,000
Desired inventory (units), August 31 2,000
Expected sales volume (units), August 75,000
For each unit produced, the direct materials requirements are as follows:
Direct material A ($5 per pound) 3Ibs
Direct material B ($15 per pound) 1/2 Ib
The number of pounds of matierials A and B required for August production are_____. The total direct materials purchases of materials A and B required for August production is:______.

Answer :

Answer:

Instructions are below.

Explanation:

Giving the following information:

Production:

Estimated inventory (units), August 1 12,000

Desired inventory (units), August 31 2,000

Expected sales volume (units), August 75,000

For each unit produced, the direct materials requirements are as follows:

Direct material A ($5 per pound) 3Ibs

Direct material B ($15 per pound) 1/2 Ib

First, we need to determine the number of pounds required.

Production= sales + desired ending inventory - beginning inventory

Production= 75,000 + 2,000 - 12,000= 65,000 units

Purchases in pounds:

Direct material A= 65,000*3= 195,000

Direct material B= 65,000*0.5= 32,500

Total pounds= 227,500

Now, the cost of direct material:

Direct material cost:

Direct material A= 195,000*5= $975,000

Direct material B= 32,500*15= $487,500

Total= $1,462,500

Other Questions